WILLIAM M. HOEVELER, Senior District Judge.
THIS CAUSE comes before the Court to determine whether the United States Army Corps of Engineers complied with the Clean Water Act, 33 U.S.C. § 1251 (CWA), National Environmental Policy Act, 42 U.S.C. § 4321 (NEPA), and the Administrative Procedure Act, 5 U.S.C. § 706(APA), when it issued permits in 2002 to several limestone mining corporations for the discharge of dredged or fill material into wetlands in Miami-Dade
In granting summary judgment for the Plaintiffs in 2006, the Court concluded that the Corps did not comply with its statutory and regulatory obligations. Sierra Club v. Flowers, 423 F.Supp.2d 1273 (S.D.Fla. 2006). After hearing argument from all sides regarding the appropriate remedy, the Court then issued a second order vacating the permits. Sierra Club v. Strock, 495 F.Supp.2d 1188 (S.D.Fla.2007). On appeal by the Intervenors, the Eleventh Circuit vacated, in part, the Court's summary judgment order,
The facts of this dispute have been addressed in detail on previous occasions. Briefly, this case is about a group of limestone mining corporations seeking permits under § 404 of the CWA to excavate limestone in a 54,000 acre area at the northwestern edge of Miami-Dade County and in areas near Everglades National Park. The area is primarily wetlands overlying the Biscayne Aquifer, the main source of drinking water for Miami-Dade County.
The Corps issued the permits in April 2002, see Record of Decision (ROD), found at Administrative Record 1028 (AR1028), for a period of ten years, authorizing approximately 5,400 acres of wetlands to be converted to mining pits. The Corps' approval relied on an Environmental Impact Statement (EIS), AR614, issued two years earlier, which addressed the miners' original proposal for fifty years of mining and a total of 14,300 acres of destroyed wetlands, AR65. That EIS was criticized by a number of agencies, organizations, and individuals, and, as a result, the Corps reduced the initial term of these permits to ten years, with the stated intention of issuing additional permits in the future.
After the Court entered summary judgment for Plaintiffs in March 2006, the parties were granted an evidentiary hearing regarding what should occur while the Corps was preparing an SEIS and considering whether to reauthorize the permits, withdraw the permits, or take some other action. During that phase of the case, the
The CWA claims before the Court relate to whether the Corps was arbitrary or capricious in determining that no practicable alternatives existed. The NEPA claims are whether the EIS met NEPA's requirements and whether the Corps' determination that the ten year permits would have no significant effect (beyond the effects studied in the original EIS) was arbitrary, capricious, or an abuse of discretion.
A court shall "hold unlawful and set aside agency action, findings, and conclusions found to be ... arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law or without observance of procedure required by law." 5 U.S.C. § 706(2)(A).
In issuing 404(b) permits the Corps' decisionmaking authority is governed substantively by the CWA and procedurally by both the CWA and NEPA. The primary focus of the analysis that follows is the CWA, although I have annotated that analysis with selected provisions of NEPA.
The CWA imposes requirements on the Corps when deciding whether to issue permits for the discharge of dredged or fill material into wetlands.
The 404(b)(1) Guidelines prohibit the Corps from issuing a 404(b) "dredge or fill" permit if the proposed project can be developed without disturbing wetlands, that is, if an environmentally preferable and practicable alternative exists. 40 C.F.R. 230.10(a). In addition to the 404(b)(1) Guidelines, the Corps' own CWA regulations also specifically require the Corps to consider practicable alternative locations and methods for accomplishing the project's objective, see 33 C.F.R. 320.4(a)(2)(ii). A practicable alternative is one that is "available and capable of being done after taking into consideration cost, existing technology, and logistics in light of overall project purposes." 40 C.F.R. 230.10(a)(2).
The Corps also must follow the procedures imposed by NEPA. NEPA's purpose is to "promote efforts which will prevent or eliminate damage to the environment." 42 U.S.C. § 4321. The statute contains procedural directives to "insure that [high quality] environmental information is available to public officials and citizens before decisions are made and before actions are taken." 40 C.F.R. 1500.1(b). "Accurate scientific analysis, expert agency comments, and public scrutiny are essential to implementing NEPA," id., and "Federal agencies must comply with both the letter and spirit of the statute," 40 C.F.R. 1500.1(a). The statute requires the preparation of an EIS, 42 U.S.C. § 4332(2)(c), which is governed by Corps regulations found at 33 C.F.R. 230.1 and Appendix B of 33 C.F.R. Part 325, and regulations promulgated by the Council on Environmental Quality (CEQ) (40 C.F.R. Part 1500). The EIS must study alternatives to the proposed action, 40 C.F.R. 1502.14. The alternatives analysis required by NEPA is similar to the alternatives analysis required by the CWA;
The 404(b)(1) Guidelines include a specific requirement that "practicable alternatives that do not involve [wetlands] are presumed to be available" if the activity for which the permit is sought "does not require access or proximity to or siting within the special aquatic site in question to fulfill its basic purpose (i.e., is not `water dependent')." 40 C.F.R. 230.10(a)(3) (emphasis added). If the proposed activity is not water dependent, the permit applicant must rebut the presumption of environmentally preferable and practicable alternatives by clearly demonstrating the absence of such alternatives. Id.
The Corps' identification of the project purpose is essential to implementation of the CWA because the statement of the project's "basic purpose" determines whether the presumption of practicable alternatives applies, and thus whether the applicant has the burden of clearly demonstrating that there are no such alternatives. 40 C.F.R. 230.10(a)(3). See, e.g., Nat'l Wildlife Fed'n v. Whistler, 27 F.3d 1341, 1345 (8th Cir.1994) ("Central to evaluating practicable alternatives is the determination of a project's purpose."). A conclusion that the project's basic purpose "require[s] access or proximity to or siting within the special aquatic site in question to fulfill its basic purpose," must be supported by the record. In this case, the Corps concluded that the project's basic purpose, limestone excavation, is water dependent. Plaintiffs have challenged that conclusion, and this Court must resolve the dispute by examining the record and any relevant authority to determine whether the Corps' decision was arbitrary or capricious.
The Corps stated in the ROD that the "basic purpose" of this project was "to extract limestone." AR1028 at 8. This decision is entitled to deference. Having established the project's basic purpose, the Corps then had to decide whether the activity is water dependent. 40 C.F.R. 230.10(a)(3).
The water dependency test prevents the Corps from approving environmentally harmful activities in wetlands if those activities might otherwise be relocated to upland locations. Permit applicants can rebut the presumption that environmentally preferable locations exist by clearly demonstrating that there are no practicable alternatives to the proposed activity. Here, the Corps concluded, without explanation, that "[t]he activity needs to be located in a special aquatic site to fulfill its basic purpose," AR1028 at 59.
Neither the CWA nor its implementing regulations list examples of "water dependent" activities, nor does the definition of a
Army Corps of Engineers Standard Operating Procedures for the Regulatory Program (October 15, 1999), cited in Fla. Clean Water Network, Inc. v. Grosskruger, 587 F.Supp.2d 1236 (M.D.Fla.2008).
In this case, the Corps first announced in the EIS, without any explanation, that "[b]y nature of the project, it involves work in wetlands, and no practicable alternative to working in wetlands exists," AR614 at 103. The Corps repeated that conclusion in the ROD: "[t]he activity needs to be located in a special aquatic site to fulfill its basic purpose." AR1028 at 59. Absent some explanation by the Corps, however, the Court is unable to defer to the Corps' unsupported conclusion that this limestone mining is water dependent,
The Corps' water dependency conclusion in this case is also at odds with its reported decisions as to what constitutes water dependent activities in other cases. As stated in the Corps' standard operating procedures, noted above, construction of a dam, marina, mooring facility, or dock necessarily involve bodies of water. Reported decisions provide additional examples: Nat'l Wildlife Fed'n v. Whistler, 27 F.3d 1341, 1345-46 (8th Cir.1994) (providing boat access to a housing development); Korteweg v. United States Army Corps of Eng'rs, 650 F.Supp. 603, 605 (D.Conn. 1986) (boat slips for residential development); Friends of the Earth v. Hintz, 800 F.2d 822, 835 (9th Cir.1986) (constructing a sorting yard for logs waiting to be transported by ocean cargo carriers).
On the other hand, the Corps has concluded, and reviewing courts have agreed, that other activities are not water dependent: Shoreline Assoc. v. Marsh, 555 F.Supp. 169 (D.Md.1983), aff'd. 725 F.2d 677 (4th Cir.1984) (construction of townhouse community); Great Rivers Habitat Alliance v. United States Army Corps of Eng'rs, 437 F.Supp.2d 1019, 1028-30 (E.D.Mo.2006) (construction of flood control levee and road improvements for a mixed-use development); Northwest Bypass Group v. United States Army Corps of Eng'rs, 552 F.Supp.2d 97, 108-109 (D.N.H.2008) (construction of roadway), and Hoosier Envt'l. Council v. United States DOT, 2007 WL 4302642, 2007 U.S. Dist. LEXIS 90840 (S.D.Ind.2007) (highways); Kentuckians for the Commonwealth v. Rivenburgh, 206 F.Supp.2d 782, 804 (S.D.W.Va.2002) (surface coal mining); and Bering Strait Citizens for Responsible Resource Development v. United States Army Corps of Eng'rs, 524 F.3d 938, 947 (9th Cir.2008) (gold mining). The Court's review of the Corps' conclusions in these cases is illuminating, and provides context in considering the Corps' analysis in this case.
Nothing in the administrative record indicates that the basic purpose of this project, limestone excavation, requires siting within wetlands. Nor do any of the Corps' prior positions suggest that limestone excavation is a water dependent activity.
The Corps has a duty to independently evaluate practicable alternatives to the proposed project "if such alternatives would have less adverse impact on the aquatic ecosystem [and no] other significant adverse environmental consequences." 40 C.F.R. 230.10(a). See also, Fund for Animals, Inc. v. Rice, 85 F.3d 535, 543.
The Corps determined, as to these permits, that the "overall project purpose is to provide construction-grade limestone from Miami-Dade County." AR1028 at 8.
In response to these federal agency concerns and public comments, the Corps obtained a report from the permit applicants, and published that report as Appendix I of the EIS, AR614 at 923 ("Analysis of the `Practicability' of Non-Lake Belt Alternative Sources to Supply Florida's Demand for Basic Construction Materials," December 1999). The report, submitted by Paul Larsen on behalf of the mining interests, AR583, was accepted by the Corps without critical review or verification
There is no indication that the Corps independently investigated Larsen's claims or the alternative sources which were identified by others — indeed, the Corps'
Even after the EIS was published, the record indicates that the Corps did nothing else to address the question of practicable alternatives. Not a single alternative location is identified by name in the ROD. The ROD included a brief summary of the alternatives discussion in the EIS:
AR1028 at 38-39 (emphasis added). The ROD also repeats the Larsen report's conclusions: "Rock product is only available in limited portions of the State. Slightly over 40% of the rock used in Florida comes from the Lake Belt. . . . Any change in the cost or availability will have wide repercussions across the state," AR1028 at 38, and "other locations would result in impacts to other ecosystems, and probably to a greater extent than in the Everglades since the area of mining would have to be larger and the other ecosystems are smaller than even the remaining extent of the Everglades," AR1028 at 84. These summary statements do not reveal that the Corps conducted an independent review of whether practicable alternatives existed, as required by 33 C.F.R. Part 325, App. B(9)(b)(4), and Fund for Animals, Inc. v. Rice, 85 F.3d at 543.
The record before me in this case fails to show that the Corps exercised independent judgment in rejecting all practicable alternatives to this proposed mining, particularly when compared to administrative records reviewed favorably by other courts. Noting the Corps' duty to conduct its own evaluation, the court in Fund for Animals, Inc. v. Rice, 85 F.3d 535, 543, upheld the Corps' permitting decision where the
Based on the record before me, I find that the Corps' conclusory statement that "there are no practicable nor less damaging alternatives which would satisfy the project's overall purpose," AR1028 at 59, and the lack of justification in the record, does not demonstrate that the Corps independently evaluated the question of practicable alternatives as required by 33 C.F.R. 325 App. B(9)(b)(4). "Alternatives might fail abjectly on economic grounds. But the Corps and, more important, the public cannot know what the facts are until the Corps has tested its presumption." Simmons v. United States Army Corps of Eng'rs, 120 F.3d 664, 669-670 (7th Cir. 1997) (vacating permit because Corps failed to evaluate entire category of reasonable alternatives for water supply). Also, the Corps' reliance on the Larsen report without independent evaluation of its claims does not comply with the requirements of NEPA, specifically 40 C.F.R. 1506.5(a), and provides further support for my conclusion that the Corps was arbitrary and capricious in concluding that there are no practicable alternatives to this mining.
In summary, after a deferential review of the Corps' unexplained decision that the activity proposed by these applicants required siting within wetlands, I find that the Corps' decision that this mining was water dependent was arbitrary and capricious, and plainly inconsistent with 40 C.F.R. 230.10(a). It is clear from the record that the Corps uncritically accepted the miners' assertions that limestone mining required siting in these specific wet-lands,
Insofar as the CWA practicable alternatives analysis is concerned, the Corps' decision to grant these permits was arbitrary and capricious. Plaintiffs are entitled to summary judgment. Moreover, the conclusions reached by the Corps did not comply with the procedural safeguards of the CWA and NEPA regulations which control the Corps' activities, as noted above, and on that separate and independent basis are arbitrary and capricious. Plaintiffs are entitled to summary judgment.
Apart from the analysis required under the CWA as to practicable alternative locations for the proposed limestone mining, NEPA also directs the Corps to evaluate alternatives which include, e.g., taking "no action" by denying the permits, or any reasonable alternatives, in order to "sharply defin[e] the issues and provid[e] a clear basis for choice among options by the decisionmaker and the public." 40 C.F.R. 1502.14. The EIS must demonstrate that the Corps complied with NEPA's requirements to "[rjigorously explore and objectively evaluate all reasonable alternatives, and for alternatives which were eliminated from detailed study, briefly discuss the reasons for their having been eliminated." 40 C.F.R. 1502.14(a).
The "no action" alternative of revoking the then-existing permits (and denying any future mining permits) was dismissed because of "the legal issues arising from" such action by the Corps, and the "economic hardships imposed on the mining industry." AR614 at 71. Similarly, the ROD dismissed the "no action" alternative:
AR1028 at 37. Based on the Corps' statements quoted above, it is clear that the Corps' decision to issue the permits was at least in part based on the Corps' belief that financial costs to the United States, i.e., from inverse condemnation actions by the miners (which may or may not succeed), might result from any prohibitions or limits on the proposed limestone mining.
The Corps apparently thought that the risk of this outcome was unacceptable, and therefore narrowed the universe of possible alternatives to those that would allow the miners to mine their property. After rejecting the "no action" alternatives, the Corps concluded that: "[t]he proposed 10-year mining footprint is the least damaging to the aquatic ecosystem in that it is much smaller than the 50-year total plan (which itself minimizes impact to wetlands compared to other alternatives described in the fifty year analysis)." AR1028 at 36-40, 55. As the Corps presently is preparing an SEIS, and in light of the Court's finding, discussed above, that the Corps' analysis of alternatives under the CWA was arbitrary and capricious, the Court need not further address the merits of the Corps' "no action" alternatives analysis at this time.
NEPA has been interpreted to require that courts "ensure that the agency took a `hard look' at the environmental consequences of the project," City of Oxford v. F.A.A., 428 F.3d 1346, 1352 (11th Cir.2005). The CWA also "requires that an environmental concern . . . be considered at an early enough stage in the policymaking process to affect the agency decision," Sierra Club v. United States Army Corps of Eng'rs, 772 F.2d 1043, 1051 (2d Cir.1985). The Corps' CWA regulations require that analysis of a proposed activity begin with the presumption that the "unnecessary alteration or destruction of [wetlands] should be discouraged as contrary to the public interest," 33 C.F.R. 320.4(b)(1), and impacts to those wetlands which perform functions "important to the public interest" should be avoided, 33 C.F.R. 320.4(b)(2). The 404(b) Guidelines also provide that the "guiding principle should be that degradation or destruction of special sites may represent an irreversible loss of valuable aquatic resources" and "is considered to be among the most severe
Permits should not issue under the CWA for activities that will cause or contribute to "significant degradation" of the wetlands at issue, 40 C.F.R. 230.10(c), [e.g., activities which might cause significantly adverse effects on municipal water supplies, wildlife habitat, etc., 40 C.F.R. 230.10(c)(1), (3)]. The statute specifically provides that unacceptable adverse effects on municipal water supplies are sufficient grounds for denial of a 404(b) permit, 33 U.S.C. § 1344(c), and pertinent regulations direct that the Corps consider water quality and water supply issues as part of its "Public Interest Review," 33 C.F.R. 320.4(a)(1).
During the preparation of the EIS and prior to issuance of the ROD, the Corps was urged by several local agencies to address the potential adverse effects on Miami-Dade County's municipal water supply from the proposed limestone mining activity, and the costs associated with mitigating those effects. The Court must decide whether the Corps considered, as required by the CWA and its implementing regulations, as well as NEPA, the significant adverse effects on municipal water supplies (which were a reasonably foreseeable result of this mining).
The county protects the quality of the Northwest Wellfield by enforcing protection zones around the production wells, based on the theoretical distance a pollutant might travel toward a production well during a specific number of days. AR1175, p. 6, 9. Limestone mining, which removes the rock and leaves pits which fill with water, affects the effectiveness of those protection zones:
AR1176 ("Description and Analysis of Full-Scale Tracer Trials Conducted at the Northwest Wellfield, Miami-Dade County Florida," Miami-Dade County environmental department report, August 2000).
One of the County's most important concerns is that the Aquifer not be subject to reclassification as "groundwater under the direct influence" of surface water-such a reclassification (from the present classification as "groundwater") would require a costly modification of the County's water treatment facilities. AR1175 (Northwest Wellfield Watershed Protection Plan, prepared for the State water agency by Miami-Dade County's environmental department, August 16, 2000). The County's municipal water department criticized the draft EIS as follows:
AR608 (letter from Director, Miami-Dade Water and Sewer Department, to Corps, May 28, 1999).
The EIS identifies three mitigation measures to protect the wellfields: the construction of a berm around the larger mining area to prevent direct entry of surface water runoff, the prohibition of future development, and the use of land use regulations to prevent urban runoff into the wellfield, AR614 at 82-83. The EIS does not include mitigation measures to address the risk of the Aquifer becoming contaminated by the mining itself, and is silent as to the estimated cost for upgrades to the County's water treatment systems which would be necessary if the Aquifer is reclassified as groundwater under the direct influence of surface water.
NEPA and its regulations impose a duty on the Corps, when evaluating "the environmental impact of the proposed action," 42 U.S.C. § 4332(2)(C)(i), to provide all available information that is "essential to a reasoned choice among alternatives," 40 C.F.R. 1502.22. By failing to include in the EIS the County's estimates of the costs of the potential upgrades to the water treatment system, or any analysis by the Corps as to whether such upgrades were reasonably foreseeable, the Corps did not comply with NEPA's regulations.
After reviewing the EIS and the Corps' Public Notice of the intent to issue the permits, the County advised the Corps that:
AR654 (letter from Miami-Dade County to Corps, July 19, 2000); see also AR656
In the alternatives analysis, the ROD includes the statement that "[i]f the wellfield is reclassified to [ground water under the influence of surface water] existing water treatment plants would have to be upgraded," AR1028 at 54, without mentioning the estimated costs of the upgrade — a secondary or indirect effect of the proposed mining activity. Although the Corps identifies the potential contamination as a secondary effect, "[t]he removal of the rock and muck increase the potential that contaminants from runoff could enter the aquifer and reach the public wellfield," it does not discuss mitigation of those adverse environmental impacts, 40 C.F.R. 1502.16, instead claiming that the risk will be reduced by "additional restrictions," AR1028 at 59.
The Corps' evaluation of the 404(b)(1) Guidelines concludes that "there are no factors . . . that would cause an adverse water quality impact," AR1028 at 57,
As discussed above, I have determined that the Corps acted arbitrarily and capriciously in concluding that this limestone excavation is water dependent and that no practicable alternatives existed. The Corps failed to articulate any explanation for its determination that the basic purpose of this project was water dependent, and failed to document any "analysis" of the practicable alternatives to this proposed mining, in violation of both the CWA and NEPA. Moreover, by failing to hold these limestone corporations to the test of "clearly demonstrating" the absence of practicable alternatives, the Corps failed to comply with 40 C.F.R. 230.10(a)(3).
The EIS also failed to meet NEPA's requirements because the Corps adopted challenged data and conclusions submitted by the permit applicants without independent evaluation, and omitted pertinent information related to the anticipated cost of upgrades to the water treatment plants. Based on the record before the Court, the Corps was arbitrary and capricious in determining that the ten year permits would have no significant effect other than identified in the EIS, in part because the EIS itself was insufficient to meet NEPA's demands.
The Corps failed to comply with statutory and regulatory directives and was arbitrary and capricious in its decision to issue the permits. The Corps' decision to issue these permits in 2002 must be set aside. The Court's decision today, and in the past, has been based on a full review of the record before me, and my understanding of the law. I have approached this case, as any other, with the intent to fulfill my commission as a judge fairly and fully, to the best of my ability.
AR614 at 69. The Corps describes the Nicholas report as a "detailed discussion of the economic significance of Lakebelt mining activities and products" and portions of the EIS, including the text above, are copied verbatim from the consultant's report, without any recorded attempt to verify the information despite criticism from another federal agency that the "information in the Economic Appendix may have overly relied on data supplied by the industry and its representatives." AR614 at 915. The Environmental Protection Agency sought "independent assessment of the economic consequences of limestone mining from a source or sources with less obvious bias." Id. Although the Nicholas report disclosed that its "methodology . . . was to distribute a written questionnaire to Lake Belt mining interests that constitute approximately 90% of mining and related activities within the Lake Belt," AR614 at 871, the Corps defended its total reliance on the report: "[the] economic analysis followed accepted principals [sic] and used the RIMMS methodology by the Department of Commerce . . . . [and we] rely on the professionalism of the prepares [sic] of the analysis unless we see or are advised of an irregularity." Id. NEPA requires that the Corps evaluate reasonably foreseeable significant adverse effects, and consider "the environmental impact" of the proposed action, 42 U.S.C. § 4332(2)(c)(I). One court has observed that misleading information about economic impacts can defeat the "hard look" function of an EIS required by NEPA. South Louisiana Environmental Council, Inc. v. Sand, 629 F.2d 1005 (5th Cir.1980).
AR637. The Court did not find this statement in the EIS or ROD.